Project review

The emergency treatment project of 5000TPDmunicipal sewage was completed.

This project was started in December 2017,adopted 10 sets of MBR integrated sewage treatment equipments, the treatmentcapacity is 5000tpd, the amount for each set of equipment is 500tpd.

The original process used in domesticsewage treatment plant is oxidation ditch process.

With the improvement of Chinese waterdischarge standard, the original process did not reach the standard, so thatthe sewage needed to be deeply treatment.

Combined with years of engineeringexperience, We suggest that the following process be adoptedA/O+MBR+UV disinfection.

The equipment components involved in thewhole process are assembled into an integrated equipment, and the installationand operation is simple.

The water parameters is as follows:

Item

CODcr

BOD5

NH3-N

TN

TP

SS

pH

mg/L

mg/L

mg/L

mg/L

mg/L

mg/L

-

Influent

350

180

35

45

4

200

6~9

Effluent

50

10

58

15

0.5

10

6~9